The FANC authorises restart of Doel 3 and Tihange 2 reactors
Transcrição
The FANC authorises restart of Doel 3 and Tihange 2 reactors
PRESS RELEASE Brussels, 17th November 2015 The FANC authorises restart of Doel 3 and Tihange 2 reactors On 17 November 2015, the Federal Agency for Nuclear Control (FANC) authorised the licensee Electrabel to restart the Doel 3 and Tihange 2 reactor units. Both reactors have been shut down for some time now because of concerns about their safety. The uncertainty about the safety of these reactors was due to the discovery of thousands of flaw indications in the steel walls of their reactor pressure vessels, during their scheduled outage in the summer of 2012. Further investigation revealed that these flaw indications had been caused by hydrogen bubbles. These bubbles had become trapped in the material when the steel rings for the pressure vessel were manufactured and then rolled out into hydrogen flakes with an average length of 12 to 16 millimetres and the thickness of a cigarette paper. These cracks are known as hydrogen flakes. The hydrogen flakes are laminar, which means they run parallel with the wall of the pressure vessel and so do not actually ‘pierce’ it. After these cracks were discovered, the FANC decided to prohibit Electrabel from restarting the Doel 3 and Tihange 2 reactors until it could prove conclusively that the safety of the reactors was not at risk due to the presence of the hydrogen flakes. The evidence for this had to be provided in the form of a Safety Case for each reactor. These Safety Cases would be assessed by the FANC and various teams of national and international experts. In December 2012, Electrabel submitted the first Safety Case reports, which were later supplemented with addenda. In May 2013, on the basis of the evidence provided in these documents and the recommendations of independent experts, the FANC authorised Electrabel to restart both reactors. A condition was that the licensee was required to complete a series of studies and measures before the end of the first reactor cycle, i.e. within approx. 1 year of the restart. In March 2014, Electrabel reported that one of these compulsory studies, the fracture toughness test, had produced unexpected results. As a precautionary measure, Doel 3 and Tihange 2 were subsequently shut down again. The FANC required the licensee to submit a new Safety Case for both reactors to justify a restart. These Safety Case reports were once again submitted to a large number of national and international experts, including the US Oak Ridge National Laboratory. The FANC collected together and analysed the reports and recommendations of the various teams of experts in order to come to its own conclusions. The FANC concludes that Electrabel has demonstrated that the hydrogen flakes in the walls of the reactor vessels do not pose an unacceptable safety risk for the reactors. Electrabel is therefore authorised to restart and operate the Doel 3 and Tihange 2 reactors until they are FANC – Ravensteinstreet 36, 1000 Brussels – www.fanc.fgov.be T : +32 (0)2 289 21 11 – F : +32 (0)2 289 21 12 – E : [email protected] permanently decommissioned. By law this is planned on 1 October 2022 for Doel 3 and on 1 February 2023 for Tihange 2. The FANC wishes to emphasise that both the Safety Case reports submitted by Electrabel and the final decision to authorise the restart are based on extensive scientific studies. These studies have provided us with certainty that the hydrogen flakes in the reactor vessels of Doel 3 and Tihange 2 have been correctly detected and sized, and that the presence of hydrogen flakes does not jeopardise the safety of the nuclear plants. The file on Doel 3 and Tihange 2 is highly complex and difficult to explain in a standard brief press release. For this reason, we have provided a more detailed chronological overview and scientific background to the case below. Although this is by no means a comprehensive overview, it may help you to understand this case better. Should you have any further questions after reading this overview, please contact the FANC spokespersons: Nele Scheerlinck (NL, ENG): +32 (0)2 289 20 17 Sébastien Berg (FR, NL): +32 (0)2 289 20 30 Dirk Vandriessche (ENG, DU): +32 (0)2 289 20 34 You can also find more information on our website: www.fanc.fgov.be. All news and press releases that the FANC has published on this case can be found on the overview page. There is also an extensive FAQ and you can find all other documents that the FANC has published related to this case: Electrabel’s Safety Cases, FANC’s evaluation reports and the reports and recommendations of the experts we consulted. FANC – Ravensteinstreet 36, 1000 Brussels – www.fanc.fgov.be T : +32 (0)2 289 21 11 – F : +32 (0)2 289 21 12 – E : [email protected] Case chronology and scientific background Summer 2012: discovery of flaw indications In the summer of 2012, the reactor pressure vessel of Doel 3 was inspected using ultrasonic probes as part of a scheduled safety review. The aim of such an ultrasonic inspection is to test the reactor pressure vessel for the presence of ‘under-clad defects’ (gaps between the steel and inox inner surface of the reactor pressure vessel). No under-clad defects were found, but the ultrasonic test did reveal other unexplained flaws inside the steel wall of the reactor pressure vessel. It was subsequently decided to prohibit Doel 3 from restarting until the nature and source of the flaw indications was identified. In September 2012, the reactor pressure vessel of Tihange 2, that was manufactured by the same company (Rotterdamsche Droogdokmaatschappij), was subjected to the same ultrasonic testing. Tihange 2 proved to have similar flaw indications to Doel 3. The flaws were soon revealed to be hydrogen flakes. When steel components are manufactured, there is a risk of excess hydrogen building up in the cast steel during the process of cooling and curing. When the hydrogen evaporates it leaves behind tiny bubbles in the steel. In this case, the bubbles were rolled flat into “hydrogen flakes” during the forging process, with an average length of 12 to 16 mm and the thickness of a cigarette paper. The hydrogen flakes are laminar, which means they run parallel to the curve of the wall of the reactor pressure vessel. The occurrence of hydrogen flakes in steel structures is a well-known and widely studied phenomenon in metallurgy. However, this was the first time the phenomenon had been observed in the walls of the reactor pressure vessel of a nuclear power plant in operation. Following this discovery, the FANC ordered that the Doel 3 and Tihange 2 nuclear reactors were not to be restarted until Electrabel had conclusively proved that the presence of the hydrogen flakes did not form a risk for the integrity and hence the safety of the reactor pressure vessels. May 2013: The FANC authorised restart Following a series of extensive studies, Electrabel submitted two Safety Case reports in December 2012, in which it argued that the safety of Doel 3 and Tihange 2 was not at risk due to the presence of hydrogen flakes in the walls of the pressure vessels. In January 2013, the FANC concluded that there was no cause for permanent shutdown of these plants, however they did require that Electrabel provide them with additional information. The licensee subsequently submitted two addenda to the Safety Case reports. In May 2013, after carefully analysing the case documents and consulting with various national and international experts, the FANC concluded that the evidence provided by Electrabel was sufficient to guarantee the safe operation of the Doel 3 and Tihange 2 reactors. On 17 May 2013, the FANC authorised the restart of the reactors. FANC – Ravensteinstreet 36, 1000 Brussels – www.fanc.fgov.be T : +32 (0)2 289 21 11 – F : +32 (0)2 289 21 12 – E : [email protected] However, they did set a number of additional conditions on this authorisation. Among others, the licensee was required to complete a series of actions before the end of the first reactor cycle (approx. 1 year after the restart). March 2014: fracture toughness test produced unexpected results One of the measures that Electrabel had to complete before the end of the first reactor cycle involved mechanical testing of irradiated steel components affected by hydrogen flakes. The aim of these tests was to find out to what extent exposure to intensive radiation influences the mechanical properties of steel that contains hydrogen flakes. Electrabel was required to conduct these tests in order to empirically confirm some hypotheses and calculations in its Safety Case reports. The tests used samples provided by a French steam generator (“VB-395”) that was constructed for use in a nuclear power plant but was rejected because the steel contained hydrogen flakes. The samples were first placed in the research reactor of the Belgian Nuclear Research Centre (SCK•CEN) in Mol, where they were intensively irradiated for four weeks in order to simulate the cumulative radiation exposure of 40 years of operation. The samples were then subjected to a series of tests to evaluate their mechanical properties. All the tests produced the expected results, with the exception of one test: the fracture toughness test. The results of this test suggested that the steel of the VB-395 specimen would become brittle much faster than expected based on theory. Because the researchers did not have an immediate explanation for these unexpected test results, it was decided on 25 March 2014 to shut down the Doel 3 and Tihange 2 reactors again as a precautionary measure. The FANC ordered that the reactors were not to be restarted until Electrabel had conclusively proved that the conclusion of 2013 remains valid (the presence of hydrogen flakes has no negative impact on the safety of the installations) despite the unexpected test results. During the following months, Electrabel commissioned SCK•CEN to conduct a number of new tests. Because the study of the mechanical properties of irradiated materials is a highly specialised research domain, the FANC called in the help of a number of leading international experts in this area to review this particular aspect of the Safety Case. This team of experts (the International Review Board) was asked to recommend an appropriate methodology to Electrabel for those parts of the Safety Cases that were related to the mechanical properties of steel under the influence of radiation. February 2015: number of detected hydrogen flakes re-evaluated Alongside the mechanical tests, Electrabel was also required to complete a number of other actions. A number of these actions were related to the qualification of the ultrasonic testing method with which the hydrogen flakes were discovered in the summer of 2012. Electrabel FANC – Ravensteinstreet 36, 1000 Brussels – www.fanc.fgov.be T : +32 (0)2 289 21 11 – F : +32 (0)2 289 21 12 – E : [email protected] was required to provide more evidence that the testing method used was capable of detecting and accurately sizing all the hydrogen flakes. The new tests revealed that the ultrasonic inspection method had indeed identified most of the flaw indications, but that the detection thresholds needed to be adjusted in order to be able to guarantee that literally every hydrogen flake was detected. It was also concluded that the method used to interpret the test results left room for improvement. In 2014, new ultrasonic tests were conducted on the reactor pressure vessels and the results were interpreted using an alternative method. This led to the detection of some 60% more flaw indications than during the previous inspection, especially thanks to lowering the detection threshold. With thus new inspection method, the researchers also noted an increase in the average and maximum length of the falkes. This was because the new interpretation method prescribed that hydrogen flakes that were close together were to be treated as single elongated flake. The FANC called in the expertise of the certified inspection company AIB-Vinçotte to evaluate the results of the qualification of the ultrasonic testing method. July 2015: Electrabel submitted new Safety Case reports to the FANC On 17 July 2015, Electrabel submitted the new Safety Case reports for Doel 3 and Tihange 2 to the FANC. As required by the FANC, these Safety Case reports focussed on three major themes, whereby the research results of themes 1 and 2 were to support the evidence for theme 3: 1. Detecting, measuring and locating the flaw indications by means of ultrasonic tests; 2. The mechanical properties of the material containing hydrogen flakes and the evolution of these mechanical properties under irradiation; 3. The structural integrity of a reactor pressure vessel that contains hydrogen flakes. The FANC forwarded copies of the Safety Case reports to the external experts involved in the definitive safety review. The certified inspection company AIB-Vinçotte wrote an evaluation report on the first theme and the Oak Ridge National Laboratory (USA) was commissioned to conduct a thorough and independent evaluation of all hypotheses, the methodology, the calculations and the interpretation of the results and to re-do all calculations, based on its own computer codes, hypotheses and methodology. Bel V, the FANC's technical branch, conducted a separate evaluation of the entire Safety Case. Finally, a working group of four Belgian professors considered the question of whether the hydrogen flakes might grow due to the migration of hydrogen through the walls of the reactor pressure vessel. The reports of the various external experts were sent to the FANC over the following months and compared with the conclusions of the FANC’s own experts. FANC – Ravensteinstreet 36, 1000 Brussels – www.fanc.fgov.be T : +32 (0)2 289 21 11 – F : +32 (0)2 289 21 12 – E : [email protected] November 2015: the FANC authorises the restart of Doel 3 and Tihange 2 Based on its own review and the reports of the various external experts, the FANC concluded that there was no cause anymore to prevent the Doel 3 and Tihange 2 reactors from restarting. Electrabel was able to demonstrate that the unexpected test results of March 2014 were probably due to the specific material properties of the specimen that was used. Tests on another material with hydrogen flakes and on the material of the reactor pressure vessels themselves demonstrated that long-lasting irradiation will not have an abnormal impact on the mechanical properties of the reactor pressure vessels of Doel 3 and Tihange 2. The structural integrity of the reactor pressure vessels of Doel 3 and Tihange 2 complies with the safety requirements and the presence of hydrogen flakes does not pose a risk to the safety of the nuclear power plants. FANC – Ravensteinstreet 36, 1000 Brussels – www.fanc.fgov.be T : +32 (0)2 289 21 11 – F : +32 (0)2 289 21 12 – E : [email protected]