installation and alignment of 2 x electric 170 ton winches installation

Transcrição

installation and alignment of 2 x electric 170 ton winches installation
CASE STUDY
MODIFICATION
INSTALLATION AND ALIGNMENT OF 2 X ELECTRIC 170 TON
WINCHES
INSTALLATION OF THE WINCHES SUPPORTING
SUPERSTRUCTURE (70 TON)
PIPING OUTFITTING AND INSTALLATION OF ALL WINCHES
AUXILIARY MECHANICAL AND ELECTRICAL MACHINERY
SHIP: MAERSK BATTLER
SHIPOWNER: MAERSK SUPPLY SERVICE
MAIN DIMENSIONS:
-
LENGTH, OVER ALL 84.6 M
-
LENGTH, BTW. PERP. 75.0 M
-
BREADTH, MLD. 18.8 M
-
DEPTH, MOULDED 9.0 M
-
SCANTLING DRAUGHT 7.5 M
CLASS:
-
LLOYDS REGISTER OF SHIPPING
-
+100 A1, + LMC, UMS, NAV1, DP(AM)
-
"OFFSHORE TUG/SUPPLY SHIP"
SHIPYARD: EBH NAMIBIA
LOCATION: WALVIS BAY, NAMIBIA
Page 1 of 4
Sede: Estaleiro da Rocha de Conde de Óbidos, Edifício C, 1350-352 Lisboa – Portugal
Oficina: Quinta Alberto Rodrigues, Lotes 2/3, Vale Fetal, 2820-456 Charneca da Caparica
Tel. (+351) 212 742 817
Fax: (+351) 213 905 345
www.step-consolidated.com
E-Mail: [email protected]
N.I.P.C – 508 352 185 – Conservatória do Registo Comercial de Lisboa – Soc. por quotas, Lda. - Capital Social 100.000 Euros
CASE STUDY
MODIFICATION
STEP 1 - SITE SURVEY AND WORK PREPARATION
While the ship was sailing from Angola to Namibia, a small qualified travel squad joined the ship in Luanda
for dimensional control and to start dismantling the equipment and cutting the steel – All executed work
done onboard was under Class approval.
At the same time the management team settled in the shipyard for site preparation, kick-off meetings,
logistics and production plan definition between all parties.
Also a team of pipe fitters and TIG welders started the pipe spools prefabrication (CuNiFer and ASTM A106
pipes) on the shipyard pipe workshop under supervision of the Client Welding Inspector.
STEP 2 – CHALLENGES
-
Reduced time frame
Level of Quality under Class Rules and IACS Recommendations
Local resources
Supplied Outfitting/Piping Project without a proper collision analysis
STEP 3 – ACTION
STEP team (a total of 30 technicians) was able to:
- Remove the existing equipment and cut the existing structure
- Install 9 structural blocks above the main which, including a structural fresh water tank
- Install and aligned the 2 secondary winches
- Prefab and fit new sea water and fresh water lines
- Modify and loop existing main hydraulic lines and fire lines
- Fit on site 12 new switch boards and 80 meters of cable trays
STEP 4 – RESULT
-
Completion 22 days
2 x 170 ton Winches installed and aligned
+ 70 tons of steel installed
Class approved
All steel works and manufactured items approved by Class and 3rd party Inspection
Satisfied Client
Page 2 of 4
Sede: Estaleiro da Rocha de Conde de Óbidos, Edifício C, 1350-352 Lisboa – Portugal
Oficina: Quinta Alberto Rodrigues, Lotes 2/3, Vale Fetal, 2820-456 Charneca da Caparica
Tel. (+351) 212 742 817
Fax: (+351) 213 905 345
www.step-consolidated.com
E-Mail: [email protected]
N.I.P.C – 508 352 185 – Conservatória do Registo Comercial de Lisboa – Soc. por quotas, Lda. - Capital Social 100.000 Euros
CASE STUDY
MODIFICATION
Page 3 of 4
Sede: Estaleiro da Rocha de Conde de Óbidos, Edifício C, 1350-352 Lisboa – Portugal
Oficina: Quinta Alberto Rodrigues, Lotes 2/3, Vale Fetal, 2820-456 Charneca da Caparica
Tel. (+351) 212 742 817
Fax: (+351) 213 905 345
www.step-consolidated.com
E-Mail: [email protected]
N.I.P.C – 508 352 185 – Conservatória do Registo Comercial de Lisboa – Soc. por quotas, Lda. - Capital Social 100.000 Euros
CASE STUDY
MODIFICATION
Page 4 of 4
Sede: Estaleiro da Rocha de Conde de Óbidos, Edifício C, 1350-352 Lisboa – Portugal
Oficina: Quinta Alberto Rodrigues, Lotes 2/3, Vale Fetal, 2820-456 Charneca da Caparica
Tel. (+351) 212 742 817
Fax: (+351) 213 905 345
www.step-consolidated.com
E-Mail: [email protected]
N.I.P.C – 508 352 185 – Conservatória do Registo Comercial de Lisboa – Soc. por quotas, Lda. - Capital Social 100.000 Euros

Documentos relacionados

ALEJANDRO ZILLI basketball profile

ALEJANDRO ZILLI basketball profile ALEJANDRO ZILLI basketball profile Team: Instituto (Argentina) (2015-17) Uniform: Height: Position: Born: Weight: Nationality: Agency:

Leia mais

Case Study_RIG 140 - STEP

Case Study_RIG 140 - STEP Renew 2" and 6" additional seawater lines in engine room Fabricate and install additional 3” pipes to HP compressor Renew 6" drill water line in Caison 2 S Renew draw works salt and cooling water s...

Leia mais