TRAFFIC INFRA_HAMBURG_AKN Railway infrastructure

Transcrição

TRAFFIC INFRA_HAMBURG_AKN Railway infrastructure
Page 1/1
TRAFFIC
INFRASTRUCTURE
Railway infrastructure in HamburgEidelstedt, Germany
Cross-section of the trough station
The suburban line Hamburg - Kaltenkirchen (AKN Eisenbahn AG) will be extended to a
2 track line partially built in a trough structure. The design of the new station
Eidelstedt Centre corresponds to the features of a subway station.
Client:
AKN Eisenbahn AG,
Kaltenkirchen, Germany
Sellhorn provided detailed engineering and structural design for all structures of a
2.6 km long section including:
Construction Costs:
approx. 20 mill. €
•
600 r.m long rail trough, covered by 3 road bridges
•
120 r.m long subway railway station
•
3 road bridges with different spans und widths
•
commercial centre above the railway station
•
extension of existing railway bridge
•
about 900 r.m long noise protection barriers
Services:
concept,
detailed engineering,
design,
tendering, supervision
Period:
2000 - 2004
Cooperation:
ICB Hamburg, ICB Berlin
Architektur und Stadtplanung,
Braunschweig
In addition Sellhorn coordinated architectural and landscape designs, the planning and
installation of all technical facilities and security devices.
The works were completed early 2004 after 2.5 years of construction. During this
period the railway operation and the road traffic continued.
South entrance of rail trough
Project-No. 9932