January to March 2012 I. INTRODUTION This report
Transcrição
January to March 2012 I. INTRODUTION This report
LURDES MUTOLA FOUNDATION Quarterly REPORT OF ACTIVITIES Period: January to March 2012 Project name More School For Me Location Magude – Mozambique Number of girls (9th and 10th grade): 21 Monthly Budget: USD3000,00 Date 6th April´12 Reported By Victorino Adriano, CFO I. INTRODUTION This report aims to update information on the progress of program activities more school for me during the period that lasts from January to March 2012. It brings an analysis of the progress that has been done and achievements of activities planned. The new year school began on 13th January of 2012 with 21 girls of grade 10. II. PLANNED ACTIVITIES Planned Activities Achievements Actividades extra curriculares 30% (Sport & HIV Aids) – trainings per month (1) Melhorar a higiene e limpeza 100% Improve hygiene and cleanliness Mais dedicação no estudo 90% More dedication in the study Bom relacionamento entre as meninas 100% Good relationship between the girls Boa saúde para as meninas Good health and medication for girls Other activities/ Unplanned • 95% a. Implementation of Regular Activities Planned Activities Achievments Acompanhamento Académico (1º, 2º e 3º trimestre) Academic monitoring (1st, 2nd and 3rd 100% quarter) Saúde e Saneamento; 95% Health and Sanitation Actividades Extracurriculares e Tempos Livres. 50% Extracurricular Activities and Leisure Monitoria e avaliação 50% M&E Logística e compra de comida 100% Logistics and purchasing food Logística, Equipamentos e Estruturas 50% Logistics and House rennovations Segurança (2 guardas) 100% Security (2 guard) b. Special Events: • 16/1/12 – Opening new year school. • 03/2/12 – Cecilia - friends visitor and donations of school material c. Major Challenges / Constraints • Lack of car to transport the girls in case of illness; • Lack of money to pay all operating costs of the project • Lack of money to attract more girls to project; III. General situation of girls in school Grade Achievments Grade 9 100% passed with average of 13 marks Grade 10 98% passed IV. Monthly Budget/ Forecast Budget Line Personnel Social Worker: House Assistant Guard Activities Coordinator - Driver Program Manager (50%) Housing House Utilities and Renovations House Consumables Girl's Consumables Prevention & Hygiene School Materials Staple Foods Perishables Medications Program Development Costs Transportation $ maintenance Administrative costs Per Month MZN 35.125,00 9.125,00 6.000,00 5.000,00 15.000,00 9.762,13 1.801,18 7.960,96 40.662,50 3.478,50 8.885,25 16.686,00 11.134,75 478,00 19.265,00 15.760,00 3.505,00 USD 1.254,46 325,89 214,29 178,57 535,71 348,65 64,33 284,32 1.452,23 124,23 317,33 595,93 397,67 17,07 688,04 562,86 125,18 Grand Total 104.814,63 3.743,38