Nuclear Energy of Ukraine - International Atomic Energy Agency

Transcrição

Nuclear Energy of Ukraine - International Atomic Energy Agency
Nuclear Energy of Ukraine - History
1950-s Uranium Industry was started
1962 Ministry of Energy and Electrification of Ukraine was established (Ukraine – a
Republic of Soviet Union)
1965 Unique Energy System of Ukraine was established
1977 1-st Unit of Chornobyl NPP was established
1980 – 1996 commissioned 15 Units type VVER
1994 Ukraine joined Convention on Nuclear Safety
1995 Law of Ukraine on Use Nuclear Energy and Radiation Safety was accepted
1996 SE “NNEGC “Energoatom” was established
1997 Law of Ukraine on Ratification of the Convention on Nuclear Safety was accepted
2004 commissioned 2 units VVER-1000 Khmelnytskyi NPP unit 2, Rivne NPP - 4
1
National Nuclear Energy Generating
Company “Energoatom”
State Enterprise NNEGC “Energoatom”
Today the Company incorporates four operating NPPs,
representing 15 nuclear power units
with 13 835 MW of total installed capacity
SE NNEGC “Energoatom” supplies approximately 50%
of Ukraine’s demand for electricity
2
2
Nuclear Energy of Ukraine Today
4 NPPs - 15 units - Total Capacity 13 835 MWe
Rivno NPP
2 VVER-440
2 VVER-1000
Khmelnitskya
NPP
2 VVER -1000
SouthUkraine NPP
3 VVER-1000
Zaporizhzhya
NPP
6 VVER-1000
3
Perspective Investment Projects
Construction of the Central spent nuclear fuel storage
facility of the Ukrainian NPP reactors of the VVER type
Cost, investment
sources and coverage:
Contract between Holtec Int. and SE NNEGC
“Energoatom” signed in 2006.
The feasibility study was developed.
In 2009 the Cabinet of Ministers Ukraine passed a Decree
on the on adoption of the FS
In 2009 it is planned to develop a design of the main
container equipment and to prepare the main samples.
Implementation Period:
2008 – 2012.
2 years of the date of the adoption by Verkhovna Rada of
Ukraine of the resolution on changes into the Law of
Ukraine “On Decision Making Procedure for Siting, Design,
Construction of Nuclear Installations and Facilities of State
Value Intended for Radioactive Waste Management”.
4
7
Perspective Investment Projects
Construction of the Central Spent Nuclear Fuel Storage
Facility of the Ukrainian NPP reactors of the VVER type
Storage facility operation will allow to ensure the long-term
maintenance of the spent nuclear fuel (SNF) of the Ukrainian NPP
reactors of VVER type on the territory of Ukraine and to waive the
removal of SNF to Russian Federation till the solution of the issue of
the SNF reprocessing ( for the purpose of the reuse of the valued
nuclear materials) or SNF disposal in the deep geological formations
The storage design capacity must provide the
containment of not more than 17 000 fuel
assemblies of the VVER reactors during a
period of not less than 100 years
5
7
Khmelnytskyi NPP Unit 3
(Construction 75 % Complete)
6
6
Khmelnytskyi NPP Unit 4
(Construction 28 % Complete)
7
7
Construction of Khmelnytskyi NPP Units 3 and 4
To finalize construction of units 3 and 4 of
Khmelnytskyi NPP a tender was invited to select a
reactor installation design
Reactor installation design of В-392Б WWER-1000
was selected at 2008
In 2009 the Cabinet of Ministers of Ukraine passed a
Decree on the use of B-392 type reactor installation in the
power units’ design
8
8
8
Construction of Khmelnytskyi NPP Units 3 and 4
In 2010 Russia and Ukraine
agreement about cooperation in
Khmelnitsky NPP Units 3 and 4
signed bilateral
construction of
Based on the agreement Atomstroyeksport and
Energoam have signed agreement for supplying of
“Reactor Island” systems design and equipment
Activities on preparation of all related contracts and
the loan agreement are underway
9
9
9
Construction of Khmelnytskyi NPP Units 3 and 4
Key Project Milestones
Completion and approval the “Feasibility Study of
Construction of Units 3 and 4 of Khmelnytskyi NPP”
– 2012
Approval of the Law on Finalization of Construction
of Units 3 and 4 of Khmelnytskyi NPP – 2012
Approval of NPP design – 2013
Commissioning of power unit 3 – 2016
Commissioning of unit 4 – 2017
10
10
General assessment for the projects
Khmelnitsky
Units 3 & 4
Central SNF
Storage Facility
NPP on new sites
11
General assessment for key issues
Key issues
Phase 1
Phase 2
National position
Nuclear safety
Management
Funding and financing
Legislative framework
Safeguards
Regulatory framework
NPP on
new site
Phase 3
*
*
*
*
*
*
*
12
General assessment for key issues
Key issues
Phase 1
Phase 2
Radiation protection
Electrical grid
Phase 3
*
NPP on
new site
*
Human resources development
*
Stakeholder involvement
*
Site and supporting facilities
NPP on
new site
Environmental protection
*
*
13
General assessment for key issues
Key issues
Phase 1
Phase 2
Emergency planning
Security and physical protection
Nuclear fuel cycle
Radioactive waste
Industrial involvement
Procurement
NPP on
new site
Phase 3
*
*
*
*
*
*
14
NEPIO –
Ministry of Fuel and Energy of Ukraine
Cabinet of Ministers of Ukraine
Ministry of Environmental
Protection of Ukraine
REGULATORS
State Nuclear Regulatory
Committee of Ukraine
Ministry of Ukraine of Emergencies
and Affairs of Population Protection
from the Consequences of
Chornobyl Catastrophe
National Electricity
Regulatory
Commission of Ukraine
NEPIO: making decision
Ministry of Energy and Coal Industry
Nuclear Energy & Industry
NEPIO: executive
level
15
Company’s
Structure
Nuclear strategy
execution
organization
NNEGC “Energoatom” has incorporated a
separated entity “Atomprojectengineering”
dealing with planning and management of:
nuclear project management
management of new reactor installation procurement
management of spent fuel dry storage facility project
and waste treatment projects
construction and installation activities
16
Key issues need to be advanced for new site
17
Key issues need to be advanced for new site
18
View on self – assessment
12. Site and supporting facilities
Phase 1
conditions
12.1.
General
survey
of
potential
sites,
conducted
Report issued and approved identifying:
(a) Requirements for nuclear power plant site evaluation;
(b) Regional analysis and identification of potential sites;
(c) Screening of potential sites and selection of candidate sites;
(d) Comparison of candidate sites.
The requirements and screening criteria ensure adequate
protection of the public and the environment from the effects of
ionizing radiation and other factors arising from nuclear
installations and are consistent with the requirements IAEA Safety
Standards Series No. NS-R-3 [8].
Evidence that the NEPIO consultants used for nuclear power
plant site selection are competent and have experience in this area
19
View on self – assessment
12. Site and supporting facilities
National requirements for nuclear power plant site:
NP 306.2.141-2008 «General Provisions of NPP’s
Safety» (highest level document within the hierarchy of
documents on NPP safety);
NP 306.2.144-2008 “Safety Requirements of Site
Selection for Siting Nuclear Power Plant”
20
View on self – assessment
12. Site and supporting facilities
Phase 1
condition
12.2. Selected
site(s) justified
Nuclear power plant site selection report approved by the NEPIO, clearly
demonstrating:
(a) All of the candidate sites identified during the site survey have been
evaluated in order to select the site(s) for the nuclear power plant;
(b) The selected site(s) are acceptable from all aspects and, in particular,
from the nuclear safety point of view;
(c) To the noise and visual effects during the construction and operation of
the future plant have been considered;
(d) The selected site(s) do not disturb or limit the access to important
archaeological objectives and do not modify the landscape unacceptably;
(e) The selected site(s) do not affect individuals or communities, the
government and local or regional organizations;
The nuclear power site selection report contains plans for additional
studies and site investigations that will need to be performed during phase 2
in order to complete and refine the assessment of plant site characteristics
21
View on self – assessment
12. Site and supporting facilities
The Ministry of Fuel and Energy of Ukraine has
developed an NPP Site Cadastre with support of
NNEGC “Energoatom”
The cadastre is expected to be approved by the
government in 2012,
THEN
The Energoatom governed by specific sites’
features will select a reactor installation type that can
be deployed
22
Key issues need to be advanced for new site
12. Site and supporting facilities
Evidence that the site(s) identified in the
BIS are owned/available for use to the
Phase 2 condition
organization issuing the BIS.
Report demonstrating ranking of possible
12.1. Detailed site sites and basis of the chosen site or sites.
characterization
Evidence that the site(s) meets all siting
completed.
requirements
and
the
necessary
characterization studies have been completed.
23
Key issues need to be advanced for new site
24
Selection of a NPP Design for new sites
Construction of power units on new NPP sites
requires that a most suitable unit design shell be selected
Multiplication of that unit in future allows maximum
cost effectiveness due to :
• Unification of the construction projects and their
implementation procedures
• Equipment and construction cost reduction
• Increase of domestic suppliers’ involvement
25
Selection of a NPP Design for new sites
Technical characteristics of a NPP are defined in IAEA
Standards, EUR requirements and the state regulatory
and legal documents.
Activities underway on selection of a reactor
installation design:
• Evaluation of design information offered by the
leading NPP vendors
• Analysis of domestic suppliers’ capabilities to support
the project implementation
• Investigation into the power grid demands and
specificity of prospective NPP sites
26
Challenges in developing nuclear power
infrastructure
Infrastructure for existing
available for running projects
nuclear
power
is
It’s expected that the infrastructure can be used
for development NPP on new site
The infrastructure abilities to meet a new NPP
development specific need to be advanced,
particularly
in areas of HRD and stakeholders
involvement
27
Public information
SE
NNEGC
“Energoatom”
public
information department provides all PR
events using
media, internet services
public information centers
public hearings arrangements
28
Nuclear Research Institute of
National Academy of Science of Ukraine
Created in 1970
27 science and science & technical divisions
Main scientific directions
Nuclear Physics (Fundamental and Applied research in the field of nuclear science and
technique)
Atomic energy (physics of nuclear reactors and radiation safety of NPP)
Solid state physics (radiation physics of solid state and radiation material science)
Plasma physics (Fundamental and Applied researches in the field of physics and
chemistry of plasma)
Radiobiology and Radioecology (radiation monitoring at NPP influence zone, the research
of biological issues of ionized irradiation)
29
Nuclear Research Institute of
National Academy of Science of Ukraine
NRI and NPPs: fruitful cooperation many years
developed the updating technology for the irradiated surveillance samples of Sharpie VVER
reactors type
created and implemented modern system for pressure vessel neutron fluency monitoring
justified scientific guidance for the NPPs safe operation
estimated the NPPs operating biosphere impact
created the detail maps of contamination for the areas neighboring to the ChNPP on the basis of
sizeable data array concerning the long-lived radionuclide’s content (137Cs, 90Sr, 238Pu,
239+240Pu and 241Am)
done the estimations of the different factors impact on the making up of the radioactive
contamination picture
elaborated and implemented the spectrometric system СТПК-01 for the uninterrupted
radioactivity control in the primary circuit heat carrier aimed on the increasing of NPPs safe
operation
30
Nuclear Industry of Ukraine
INFRASTRUCTURE
PROSPECTING
DESIGNER
- State Enterprise “Kirovgeologya”
- D&R and Prospecting Commercial Technology Institute
URANIUM COMPLEX
MANUFECTURES
“Zirconium”
ZIRCONIUM COMPLEX
- SE “ShidGZC”,
- SE
- SE “Smoly”
- SE “Vilnogirsky GMC”
MINES
- Ingulsk, Smoline,
- under construction –
Novokonstyantinivska,
- perspective – 19
- Vilnogirsk
31
Nuclear Fuel –
Construction of Nuclear Fuel Plant
2009 Cabinet Ministries Order on State
economical programme “Nuclear fuel of Ukraine”
Goal:
to meet the NPPs fuel demand till 2030
to increase U3O8 production
Term – 2009 – 2013 years
Construction of Nuclear Fuel Plant - fuel fabrication from elements
Reconversion (UF6 UO2)
Pelletizing (UO2- pellets)
Fuel Rods Production (rods+pellets)
Fuel Assemblies Production
32
HR Development
Universities with the Nuclear Sphere Directions:
Sevastopol National University of Nuclear Energy and
Industry (SNUNEI)
National Technical University of Ukraine “Kyiv Polytechnic
Institute” (NTUU KPI)
Odessa National Polytechnic University (ONPU)
Kyiv University, Donetsk University and others
All Universities trains foreign students
33
Nuclear Energy in Ukraine Today and
Tomorrow (International Cooperation Activity)
2005 Ukraine Joined Innovative Nuclear Reactors and Fuel
Cycles Programme (INPRO). Participants - 21 countries and EC.
2005-2008 Investigation of Innovative Nuclear Energy System of Ukraine,
Report
2009-2010 Collaborate Project GAINS - Global Architecture of Innovative
Nuclear Energy Systems Based on Thermal and Fast Reactors Including a
Closed Fuel Cycle. Participants - 27 countries.
development and design of the initial data configurations of the Innovative Nuclear Energy System of Ukraine
(INESU) on the base of thermal and fast reactors with the closing of the Nuclear Fuel Cycle (national and
regional construction of INESU);
an estimation of INESU configurations variants on Sustainability, priority directions determination for the
infrastructure development, an estimation of economics and science & researching
development of the basic requirements to the reactor taking into account various INESU (U, U-Pu, U-Th,
convenient for Ukraine);
Algorithm developping on the Transferring from the Opened Fuel cycle to the Closed Fuel cycle
34
Nuclear Energy in Ukraine Today and
Tomorrow (International Cooperation Activity)
2007 Ukraine Joined GNEP –
Global Nuclear Energy Partnership
Collaboration on
the nuclear energy development for the peaceful and safe using in
the whole world, and
the development and introduction of the newest fuel cycles and
nuclear technologies
Infrastructure Development Working Group (IDWG)
Reliable Nuclear Fuel Services Working Group (RNFSWG)
35
Nuclear Energy in Ukraine Today and
Tomorrow (International Cooperation Activity)
EC-IAEA-Ukraine Joint Project: “Safety Assessment of Ukraine Nuclear
Power Plants”
In 2005 EU & Ukraine signed a MOU on cooperation in the field of energy, aimed at
integration of energy markets.
Road Map covering some areas, including Nuclear safety
“Safety Assessment of Ukraine Nuclear Power Plants” Project Objective
Within the framework of the Road Map for Nuclear Safety, an Agreement was signed with the
IAEA to assess the compliance of Ukrainian NPPs with current IAEA Safety Standards in
the following areas:
Task 1: NPP design safety;
Task 2: NPP operational safety;
Task 3: Waste management and decommissioning
Task 4: Regulatory issues
36
Nuclear Energy in Ukraine Today and
Tomorrow (International Cooperation Activity)
This is the first time that such a complete and comprehensive safety assessment
was done in the areas of the Regulatory Body and NPPs activities in a country,
is being carried out by the Agency in any Member State
RESULTS:
full compliance with most of the IAEA’s Safety
Requirements
Progress to meet the IAEA’s Standards was observed
in some of those areas where non full compliance was
identified
Similar deviations from standards, as some of those
bserved in this Project, can be find in other NPPs
worldwide
The Project is running on schedule, within estimated
budget and with a good interaction among all
stakeholders
Final Project Report approved on February 2010
37
Thank you for your kind attention and
Welcome to Ukraine!
38