AMPA-09 HP COMPRESSOR (Brunei) KimFlex Slings,and Shackles

Transcrição

AMPA-09 HP COMPRESSOR (Brunei) KimFlex Slings,and Shackles
PROJECT TITLE
AMPA-09 HP Compressor.
DATE
January 2013.
BACKGROUND
The Ampa-9 HP Compressor Project will
install 2 new HP compressor trains on the
AMCP facility,.
This project is key for
production levels to be sustained and enables
future gas opportunities to be developed,.
AMPA-09 HP COMPRESSOR (Brunei)
KimFlex Slings,and Shackles
ITEMS
•1 x KimFlex Sling, 304mm dia, x 11.96 mtr length,
MBL 3060 MT
•2 x KimFlex Slings, 304mm dia, x 11.17 mtr length,
MBL 3060 MT
•1 x KimFlex Sling, 304mm dia, x 10.46 mtr length,
MBL 3060 MT
•4 x KimFlex Slings, 284mm dia, x 12.96 mtr length,
MBL 2592 MT
•4 x KimFlex Slings, 284mm dia, x 11.65 mtr length,
MBL 2592 MT
•4 x Crosby G-2160 Wide Body Shackles, 700MT
•10 x Crosby G-2160 Wide Body Shackles, 500MT
6 x Green Pin P6033 Wide Body Sling Shackles,
500MT
All manufactured and tested by KTL Offshore in
Singapore. Witnessed and certified by ABS.